TY - JOUR
T1 - Project buffer sizing and dynamic buffer consumption algorithm in power generation construction
AU - Zohrehvandi, Shakib
AU - Khalilzadeh, Mohammad
AU - Amiri, Maghsoud
AU - Shadrokh, Shahram
N1 - Publisher Copyright:
© 2021, Emerald Publishing Limited.
PY - 2022/3/8
Y1 - 2022/3/8
N2 - Purpose: The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration. Design/methodology/approach: The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in MATLAB software. The sensitivity analysis was conducted to show the BSCA influence on project implementation. Then, to evaluate the BSCA algorithm, inputs from this project were run through several algorithms recently presented by researchers. Finally, the data of 20 projects previously accomplished by the company were applied to compare the proposed algorithm. Findings: The results show that BSCA heuristic algorithm outperformed the other algorithms as it shortened the projects' durations. The average project completion time using the BSCA algorithm was reduced by about 15% compared to the previous average project completion time. Originality/value: The proposed BSCA algorithm determines both the project buffer and feeding buffers and simultaneously controls their consumption in a dynamic way.
AB - Purpose: The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration. Design/methodology/approach: The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in MATLAB software. The sensitivity analysis was conducted to show the BSCA influence on project implementation. Then, to evaluate the BSCA algorithm, inputs from this project were run through several algorithms recently presented by researchers. Finally, the data of 20 projects previously accomplished by the company were applied to compare the proposed algorithm. Findings: The results show that BSCA heuristic algorithm outperformed the other algorithms as it shortened the projects' durations. The average project completion time using the BSCA algorithm was reduced by about 15% compared to the previous average project completion time. Originality/value: The proposed BSCA algorithm determines both the project buffer and feeding buffers and simultaneously controls their consumption in a dynamic way.
KW - Buffer management
KW - Project management
KW - Schedule management
KW - Wind farm construction project
UR - http://www.scopus.com/inward/record.url?scp=85102706236&partnerID=8YFLogxK
U2 - 10.1108/ECAM-08-2020-0605
DO - 10.1108/ECAM-08-2020-0605
M3 - Article
AN - SCOPUS:85102706236
SN - 0969-9988
VL - 29
SP - 716
EP - 738
JO - Engineering, Construction and Architectural Management
JF - Engineering, Construction and Architectural Management
IS - 2
ER -