T1 - COLLABORATIVE PLANNING OF SUBCONTRACTORS USING THE LAST PLANNER SYSTEM AND BIM
T2 - 32nd Annual Conference of the International Group for Lean Construction, IGLC 2024
AU - Brioso, Xaver
AU - Delgado, Karla
AU - Herrera, Rodrigo F.
AU - Lozano, Miguel
AU - Bravo, Luis
N1 - Publisher Copyright:
© 2025, International Group for Lean Construction. All rights reserved.
PY - 2024
Y1 - 2024
N2 - The objective of this study is to adapt the Last Planner System (LPS) for managing subcontractors in natural gas installations within repetitive housing projects, using BIM technology for enhanced modeling and efficiency. Our methodology was applied to a large-scale, multi-family, low-cost housing project in Lima, Peru. Through this application, we achieved high Percent Plan Complete (PPC) values and improved collaborative planning practices. This paper makes distinct contributions to the subcontractor management literature: (1) it demonstrates the practical integration of LPS with BIM to streamline subcontractor activities in a real-world setting; (2) it offers a novel approach for determining optimal Takt Time Planning for daily and weekly schedules, enhancing the predictability and reliability of subcontractor work; and (3) lessons learned from the implementation provide a roadmap that can be adapted to other subcontractor management scenarios.
AB - The objective of this study is to adapt the Last Planner System (LPS) for managing subcontractors in natural gas installations within repetitive housing projects, using BIM technology for enhanced modeling and efficiency. Our methodology was applied to a large-scale, multi-family, low-cost housing project in Lima, Peru. Through this application, we achieved high Percent Plan Complete (PPC) values and improved collaborative planning practices. This paper makes distinct contributions to the subcontractor management literature: (1) it demonstrates the practical integration of LPS with BIM to streamline subcontractor activities in a real-world setting; (2) it offers a novel approach for determining optimal Takt Time Planning for daily and weekly schedules, enhancing the predictability and reliability of subcontractor work; and (3) lessons learned from the implementation provide a roadmap that can be adapted to other subcontractor management scenarios.
KW - BIM
KW - continuous improvement
KW - gas facilities management
KW - Last Planner System
KW - subcontractor management
UR - http://www.scopus.com/inward/record.url?scp=105006417216&partnerID=8YFLogxK
U2 - 10.24928/2024/0222
DO - 10.24928/2024/0222
M3 - Conference article
AN - SCOPUS:105006417216
SN - 2309-0979
VL - 32
SP - 523
EP - 534
JO - Annual Conference of the International Group for Lean Construction, IGLC
JF - Annual Conference of the International Group for Lean Construction, IGLC
Y2 - 1 July 2024 through 7 July 2024
ER -