T1 - APRT-FMEA buffer sizing method in scheduling of a wind farm construction project
AU - Zohrehvandi, Shakib
AU - Khalilzadeh, Mohammad
N1 - Publisher Copyright:
© 2019, Emerald Publishing Limited.
PY - 2019/7/10
Y1 - 2019/7/10
N2 - Purpose: The purpose of this paper is to present an efficient model for project buffer sizing by taking failure mode and effects analysis (FMEA) into account to reach a more realistic schedule. Design/methodology/approach: In the first phase of the project, several turbines were installed according to the primary schedule with an average duration of 142 days. Then, some of critical chain project management algorithms were separately applied in the implementation and installation of the other wind turbines. The adaptive procedure with resource tightness (APRT) method turned out to be the best method in terms of obtaining a more realistic schedule in this case study. Finally, FMEA was simultaneously applied with APRT. Findings: Applying the hybrid method to the scheduling of the wind turbines, yielded the more realistic schedule than traditional. Research limitations/implications: The proposed hybrid APRT-FMEA algorithm was implemented on a real wind farm construction project which was completed with 37 percent shorter duration than the initial estimation; in spite of the initial estimation of 142 days, the project completed in 103 days. Practical implications: Introducing and implementing a new algorithm which is a combination of buffer sizing algorithms and one of the well-known and mostly used risk assessment methods in order to provide the more realistic project schedule in the construction of wind turbines. Originality/value: Introducing and implementing a novel algorithm which is a combination of conventional buffer sizing method and one of the efficient risk assessment methods in order to make the schedule more realistic.
AB - Purpose: The purpose of this paper is to present an efficient model for project buffer sizing by taking failure mode and effects analysis (FMEA) into account to reach a more realistic schedule. Design/methodology/approach: In the first phase of the project, several turbines were installed according to the primary schedule with an average duration of 142 days. Then, some of critical chain project management algorithms were separately applied in the implementation and installation of the other wind turbines. The adaptive procedure with resource tightness (APRT) method turned out to be the best method in terms of obtaining a more realistic schedule in this case study. Finally, FMEA was simultaneously applied with APRT. Findings: Applying the hybrid method to the scheduling of the wind turbines, yielded the more realistic schedule than traditional. Research limitations/implications: The proposed hybrid APRT-FMEA algorithm was implemented on a real wind farm construction project which was completed with 37 percent shorter duration than the initial estimation; in spite of the initial estimation of 142 days, the project completed in 103 days. Practical implications: Introducing and implementing a new algorithm which is a combination of buffer sizing algorithms and one of the well-known and mostly used risk assessment methods in order to provide the more realistic project schedule in the construction of wind turbines. Originality/value: Introducing and implementing a novel algorithm which is a combination of conventional buffer sizing method and one of the efficient risk assessment methods in order to make the schedule more realistic.
KW - Case study
KW - Construction planning
KW - Novel model
KW - Optimization
KW - Project management
KW - Scheduling
UR - http://www.scopus.com/inward/record.url?scp=85065674913&partnerID=8YFLogxK
U2 - 10.1108/ECAM-04-2018-0161
DO - 10.1108/ECAM-04-2018-0161
M3 - Article
AN - SCOPUS:85065674913
SN - 0969-9988
VL - 26
SP - 1129
EP - 1150
JO - Engineering, Construction and Architectural Management
JF - Engineering, Construction and Architectural Management
IS - 6
ER -