A fuzzy project buffer management algorithm: a case study in the construction of a renewable project

Shakib Zohrehvandi, Mario Vanhoucke, Mohammad Khalilzadeh, Maghsoud Amiri, Shahram Shadrokh

Producción científica: Contribución a una revistaArtículorevisión exhaustiva

7 Citas (Scopus)

Resumen

One of the major problems with projects is that they are not completed according to schedule. Uncertainty always exists at the heart of real-world project scheduling problems. This paper introduces a fuzzy project buffer management (FPBM) algorithm which is a combination of the adaptive procedure with resource tightness (APRT) and fuzzy failure mode and effects analysis (FFMEA) methods. This paper aims to present an efficient model for project buffer sizing by taking FFMEA into account to reach a more realistic schedule. In this research, for increasing the efficiency of the APRT method, the FFMEA technique is simultaneously applied with them. This research was carried out as a case study in a renewable energy (RE) project. The methodology of this research consists of two phases. The first phase is the implementation of the APRT buffer sizing method. In the second phase of the research methodology, the fuzzy FMEA method is implemented. To validate the proposed model, the results are compared to several buffer management models proposed recently. Also, the results were compared with the results of similar projects. The findings show that considering the fuzzy FMEA technique in the APRT method, a more realistic schedule was obtained in this project.

Idioma originalInglés
Páginas (desde-hasta)2134-2143
Número de páginas10
PublicaciónInternational Journal of Construction Management
Volumen23
N.º12
DOI
EstadoPublicada - 2023
Publicado de forma externa

Huella

Profundice en los temas de investigación de 'A fuzzy project buffer management algorithm: a case study in the construction of a renewable project'. En conjunto forman una huella única.

Citar esto