Project buffer sizing and dynamic buffer consumption algorithm in power generation construction

  • Islamic Azad University
  • AllamehTabatabai University
  • Sharif University of Technology

Research output: Contribution to journalArticlepeer-review

16 Scopus citations

Abstract

Purpose: The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration. Design/methodology/approach: The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in MATLAB software. The sensitivity analysis was conducted to show the BSCA influence on project implementation. Then, to evaluate the BSCA algorithm, inputs from this project were run through several algorithms recently presented by researchers. Finally, the data of 20 projects previously accomplished by the company were applied to compare the proposed algorithm. Findings: The results show that BSCA heuristic algorithm outperformed the other algorithms as it shortened the projects' durations. The average project completion time using the BSCA algorithm was reduced by about 15% compared to the previous average project completion time. Originality/value: The proposed BSCA algorithm determines both the project buffer and feeding buffers and simultaneously controls their consumption in a dynamic way.

Original languageEnglish
Pages (from-to)716-738
Number of pages23
JournalEngineering, Construction and Architectural Management
Volume29
Issue number2
DOIs
StatePublished - 8 Mar 2022
Externally publishedYes

Keywords

  • Buffer management
  • Project management
  • Schedule management
  • Wind farm construction project