A modified PSO algorithm for minimizing the total costs of resources in MRCPSP

Mohammad Khalilzadeh, Fereydoon Kianfar, Ali Shirzadeh Chaleshtari, Shahram Shadrokh, Mohammad Ranjbar

Research output: Contribution to journalArticlepeer-review

16 Scopus citations

Abstract

We introduce a multimode resource-constrained project scheduling problem with finish-to-start precedence relations among project activities, considering renewable and nonrenewable resource costs. We assume that renewable resources are rented and are not available in all periods of time of the project. In other words, there is a mandated ready date as well as a due date for each renewable resource type so that no resource is used before its ready date. However, the resources are permitted to be used after their due dates by paying penalty costs. The objective is to minimize the total costs of both renewable and nonrenewable resource usage. This problem is called multimode resource-constrained project scheduling problem with minimization of total weighted resource tardiness penalty cost (MRCPSP-TWRTPC), where, for each activity, both renewable and nonrenewable resource requirements depend on activity mode. For this problem, we present a metaheuristic algorithm based on a modified Particle Swarm Optimization (PSO) approach introduced by Tchomté and Gourgand which uses a modified rule for the displacement of particles. We present a prioritization rule for activities and several improvement and local search methods. Experimental results reveal the effectiveness and efficiency of the proposed algorithm for the problem in question.

Original languageEnglish
Article number365697
JournalMathematical Problems in Engineering
Volume2012
DOIs
StatePublished - 2012
Externally publishedYes

Fingerprint

Dive into the research topics of 'A modified PSO algorithm for minimizing the total costs of resources in MRCPSP'. Together they form a unique fingerprint.

Cite this